1st Report Of July 2023

July 15, 2023

Mainnet Performance

Validation nodes: 100

Mining nodes: 1198

New wallets added: 49+

Project Update

1st Part of MATRIX 3.0 Phase I – 85%

  1. Completed the first version of the development work combining EEG indicators with the MATRIX wallet;

  2. Completed the security design work of two-step verification combining brainwaves with private passwords;

  3. Completed the training and implementation of the quantitative model of brainwave attention value indicators.

Special Patches Phase I – 85%

  1. Completed the double-blind test acceptance work of the first version of the Intelligent Contract;

  2. Completed the stability optimization of some functions of the first version of the Intelligent Contract;

  3. Started the development work of the first version for the user end.

Others

  1. Completed the training work for the first phase of the next version of Morpheus.

  2. MANTA Demo-90%

  3. Ledger Integration-40%